JANUARY 2025
​
​
Building Safety
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
​
Building Safety
The Public Accounts Committee has opened an inquiry into the remediation of dangerous cladding and is inviting evidence to be submitted for them to consider, with the deadline for submissions being 11.59 on Monday 20 January
More details can be found via the link below:
​
​
​​
​
The Remediation Acceleration Plan
As a reminder, the Government announced this Plan last month, saying that:-
-
through this plan they aimed that by the end of 2029 all 18m+ (high-rise) buildings with unsafe cladding in a government funded scheme will have been remediated
-
furthermore, by the end of 2029, every 11m+ building with unsafe cladding will either have been remediated, have a date for completion, or the landlords will be liable for severe penalties.
At the same time the Government said that it would:
-
encourage and support developers to achieve their stretch target to start or complete remedial works on 80% of the buildings for which they are responsible by July 2026, and on 100% of those buildings by July 2027
-
speed up the progress of buildings in government-funded schemes by reducing the time from application to works starting on site
​
​
​
​
​
​
​
​
​
​
%201154682665.jpg)
-
Public Accounts Committee Inquiry into the remediation of dangerous cladding
-
The Remediation Acceleration Plan